Thamesmead

Heralded by the Greater London Council (GLC) as a “town for the 21st century”, the 'Woolwich-Erith Riverside Project' was only christened Thamesmead in 1967 following a 'Name Our New Town' competition with a £20 prize. To be built on marshland and part of the Woolwich Arsenal site, it was intended to help ease the capital’s post-war housing shortage and to be a town of 60,000 people exploiting a riverside position with sufficient local employment, amenities and transport infrastructure.

The 1967 master plan envisaged a combination of long spine blocks and high- rise point blocks but Thamesmead’s design and landscape was influenced by the site. Pollution from local heavy industry prohibited building above 200ft dictating squat 13-storey point blocks rather than the few intended tall, slim blocks. In 1953 the site was flooded by the North Sea inundation, thus for flood protection all habitable accommodation had to be on the first floor with garages and service areas below. The houses were innovatively linked by raised walkways also serving to separate pedestrians from road traffic. To assist in controlling water levels a series of balancing lakes and canals would drain run-off water into the Thames at low tide.

Such was the initial international attention given to Thamesmead’s architecture that the early residents found the great number of visitors highly intrusive. However, media focus on the GLC’s flagship project soon switched to its failings, in particular the urban alienation of disillusioned residents. Today its reputation is synonymous with the film 'A Clockwork Orange' but the problems predated the film’s 1971 release. The much vaunted walkways had the unintended consequence of dark no-go areas below, facilities took too long to develop, transport links were poor and contaminated land and ground conditions led to expensive construction and delays.

Despite being the culmination of the GLC’s housing works, ultimately only stages 1 and 2 were completed in a form resembling the master plan which largely remained an unrealised vision. Mostly forgotten today, much of Thamesmead, ironically, now comprises suburban housing and although there is a programme of regeneration for stages 1 and 2 this is proceeding slowly and has resulted in the demolition of the futuristic Lakeside Health Centre (Derek Stow & Partners, 1972).

50 years on from the initial construction phase this gallery is illustrated by historic photographs from the RIBA Robert Elwall Photographs Collection and the work of contemporary photographers Christopher Hope-Fitch and Joanne UnderhillView more images of Thamesmead here. All of the images are available to download, purchase or license.

Feature by Jonathan Makepeace.

View as Grid List
Sort by

Housing, Thamesmead, London: a glazed stairtower

RIBA112877
Greater London Council. Department of Architecture & Civic Design
NOTES: Thamesmead was planned in 1965-1966 as a new town on the riverside marshes of south-east London between Plumstead and Erith. It was scheduled for completion in 1974 but was never fully finished and the projected population of 60,000 for the new town was downgraded to 45,000 by the end of the 1970s. From then around 400 houses were being built annually and by 1982, the population stood at 20,000. Since 2014 the managment and regeneration of the area has come under the aegis of Peabody.

Housing, Thamesmead, London: the tower blocks and upper level walkway

RIBA112883
Greater London Council. Department of Architecture & Civic Design
NOTES: Thamesmead was planned in 1965-1966 as a new town on the riverside marshes of south-east London between Plumstead and Erith. It was scheduled for completion in 1974 but was never fully finished and the projected population of 60,000 for the new town was downgraded to 45,000 by the end of the 1970s. From then around 400 houses were being built annually and by 1982, the population stood at 20,000. Since 2014 the managment and regeneration of the area has come under the aegis of Peabody.

Linking bridges and elevated walkways, Thamesmead, London

RIBA112885
Greater London Council. Department of Architecture & Civic Design
NOTES: Thamesmead was planned in 1965-1966 as a new town on the riverside marshes of south-east London between Plumstead and Erith. It was scheduled for completion in 1974 but was never fully finished and the projected population of 60,000 for the new town was downgraded to 45,000 by the end of the 1970s. From then around 400 houses were being built annually and by 1982, the population stood at 20,000. Since 2014 the managment and regeneration of the area has come under the aegis of Peabody.

Housing at Lesnes, Thamesmead, Greenwich, London: view from Coralline Walk towards Lesnes Towers

RIBA2797-21
Greater London Council. Department of Architecture & Civic Design
NOTES: This is one of the images taken for 'Manplan 8: Housing' in Architectural Review, vol. 148, September 1970. Thamesmead was planned in 1965-1966 as a new town on the riverside marshes of south-east London between Plumstead and Erith. It was scheduled for completion in 1974 but was never fully finished and the projected population of 60,000 for the new town was downgraded to 45,000 by the end of the 1970s. From then around 400 houses were being built annually and by 1982, the population stood at 20,000. Since 2014 the managment and regeneration of the area has come under the aegis of Peabody.

High-rise housing, Thamesmead, Greenwich, London

RIBA15739
Greater London Council. Department of Architecture & Civic Design
NOTES: This is one of the images taken for 'Manplan 8: Housing' in Architectural Review, vol. 148, September 1970. Thamesmead was planned in 1965-1966 as a new town on the riverside marshes of south-east London between Plumstead and Erith. It was scheduled for completion in 1974 but was never fully finished and the projected population of 60,000 for the new town was downgraded to 45,000 by the end of the 1970s. From then around 400 houses were being built annually and by 1982, the population stood at 20,000. Since 2014 the managment and regeneration of the area has come under the aegis of Peabody.

Children playing in the precinct of low-rise housing, Tavy Bridge, Thamesmead, Greenwich, London

RIBA15741
Greater London Council. Department of Architecture & Civic Design
NOTES: This is one of the images taken for 'Manplan 8: Housing' in Architectural Review, vol. 148, September 1970. Thamesmead was planned in 1965-1966 as a new town on the riverside marshes of south-east London between Plumstead and Erith. It was scheduled for completion in 1974 but was never fully finished and the projected population of 60,000 for the new town was downgraded to 45,000 by the end of the 1970s. From then around 400 houses were being built annually and by 1982, the population stood at 20,000. Since 2014 the managment and regeneration of the area has come under the aegis of Peabody.

Gardens precinct of low-rise housing, Hinksey Path, Lesnes, Thamesmead, Greenwich, London

RIBA15742
Greater London Council. Department of Architecture & Civic Design
NOTES: This is one of the images taken for 'Manplan 8: Housing' in Architectural Review, vol. 148, September 1970. Thamesmead was planned in 1965-1966 as a new town on the riverside marshes of south-east London between Plumstead and Erith. It was scheduled for completion in 1974 but was never fully finished and the projected population of 60,000 for the new town was downgraded to 45,000 by the end of the 1970s. From then around 400 houses were being built annually and by 1982, the population stood at 20,000. Since 2014 the managment and regeneration of the area has come under the aegis of Peabody.

Low-rise housing,Thamesmead, Greenwich, London

RIBA15743
Greater London Council. Department of Architecture & Civic Design
NOTES: This is one of the images taken for 'Manplan 8: Housing' in Architectural Review, vol. 148, September 1970. Thamesmead was planned in 1965-1966 as a new town on the riverside marshes of south-east London between Plumstead and Erith. It was scheduled for completion in 1974 but was never fully finished and the projected population of 60,000 for the new town was downgraded to 45,000 by the end of the 1970s. From then around 400 houses were being built annually and by 1982, the population stood at 20,000. Since 2014 the managment and regeneration of the area has come under the aegis of Peabody.

Pepys Estate, Deptford, London

RIBA15747
Greater London Council. Department of Architecture & Civic Design
NOTES: This is one of the images taken for 'Manplan 8: Housing' in Architectural Review, vol. 148, 1970 Sep.

Onlookers by the lake watch the construction of Thamesmead, Greenwich, London

RIBA23422
Greater London Council. Department of Architecture & Civic Design
NOTES: This is one of the images taken for 'Manplan 8: Housing' in Architectural Review, vol. 148, September 1970. Thamesmead was planned in 1965-1966 as a new town on the riverside marshes of south-east London between Plumstead and Erith. It was scheduled for completion in 1974 but was never fully finished and the projected population of 60,000 for the new town was downgraded to 45,000 by the end of the 1970s. From then around 400 houses were being built annually and by 1982, the population stood at 20,000. Since 2014 the managment and regeneration of the area has come under the aegis of Peabody.

Bridge across Yarnton Way, Lesnes / Southmere, Thamesmead, Greenwich, London

RIBA23425
Greater London Council. Department of Architecture & Civic Design
NOTES: Thamesmead was planned in 1965-1966 as a new town on the riverside marshes of south-east London between Plumstead and Erith. It was scheduled for completion in 1974 but was never fully finished and the projected population of 60,000 for the new town was downgraded to 45,000 by the end of the 1970s. From then around 400 houses were being built annually and by 1982, the population stood at 20,000. Since 2014 the managment and regeneration of the area has come under the aegis of Peabody.

Maisonettes, Thamesmead, Greenwich, London

RIBA50189
Greater London Council. Department of Architecture & Civic Design
NOTES: This is one of the images taken for 'Manplan 8: Housing' in Architectural Review, vol. 148, September 1970. Thamesmead was planned in 1965-1966 as a new town on the riverside marshes of south-east London between Plumstead and Erith. It was scheduled for completion in 1974 but was never fully finished and the projected population of 60,000 for the new town was downgraded to 45,000 by the end of the 1970s. From then around 400 houses were being built annually and by 1982, the population stood at 20,000. Since 2014 the managment and regeneration of the area has come under the aegis of Peabody.

Clewer House nearing completion, Thamesmead, Greenwich, London

RIBA63027
Greater London Council. Department of Architecture & Civic Design
NOTES: This is one of the images taken for 'Manplan 8: Housing' in Architectural Review, vol. 148, September 1970. Thamesmead was planned in 1965-1966 as a new town on the riverside marshes of south-east London between Plumstead and Erith. It was scheduled for completion in 1974 but was never fully finished and the projected population of 60,000 for the new town was downgraded to 45,000 by the end of the 1970s. From then around 400 houses were being built annually and by 1982, the population stood at 20,000. Since 2014 the managment and regeneration of the area has come under the aegis of Peabody.

Blewbury House, Southmere, Lesnes, Thamesmead, London: looking toward Corraline Walk and Wolvercote Road across pedestrian bridge over Yarnton Way

RIBA70503
Greater London Council. Department of Architecture & Civic Design
NOTES: Thamesmead was planned in 1965-1966 as a new town on the riverside marshes of south-east London between Plumstead and Erith. It was scheduled for completion in 1974 but was never fully finished and the projected population of 60,000 for the new town was downgraded to 45,000 by the end of the 1970s. From then around 400 houses were being built annually and by 1982, the population stood at 20,000. Since 2014 the managment and regeneration of the area has come under the aegis of Peabody.

Tavy Bridge shops and Southmere Lake, Binsey Walk, Southmere, Thamesmead, London, seen from Tilehurst Point with Southmere Towers in the distance

RIBA70505
Greater London Council. Department of Architecture & Civic Design
NOTES: Thamesmead was planned in 1965-1966 as a new town on the riverside marshes of south-east London between Plumstead and Erith. It was scheduled for completion in 1974 but was never fully finished and the projected population of 60,000 for the new town was downgraded to 45,000 by the end of the 1970s. From then around 400 houses were being built annually and by 1982, the population stood at 20,000. Since 2014 the managment and regeneration of the area has come under the aegis of Peabody.

Housing, Thamesmead, London: the pedestrian bridge

RIBA113785
Greater London Council. Department of Architecture & Civic Design
NOTES: Thamesmead was planned in 1965-1966 as a new town on the riverside marshes of south-east London between Plumstead and Erith. It was scheduled for completion in 1974 but was never fully finished and the projected population of 60,000 for the new town was downgraded to 45,000 by the end of the 1970s. From then around 400 houses were being built annually and by 1982, the population stood at 20,000. Since 2014 the managment and regeneration of the area has come under the aegis of Peabody.

Southmere Towers, Southmere Lake, Southmere, Thamesmead, London: the tower blocks overlooking the lake with a swan in the foreground.

RIBA113788
Greater London Council. Department of Architecture & Civic Design
NOTES: Thamesmead was planned in 1965-1966 as a new town on the riverside marshes of south-east London between Plumstead and Erith. It was scheduled for completion in 1974 but was never fully finished and the projected population of 60,000 for the new town was downgraded to 45,000 by the end of the 1970s. From then around 400 houses were being built annually and by 1982, the population stood at 20,000. Since 2014 the managment and regeneration of the area has come under the aegis of Peabody.

Binsey Walk, Southmere, Thamesmead, London: the maisonette blocks

RIBA113797
Greater London Council. Department of Architecture & Civic Design
NOTES: Thamesmead was planned in 1965-1966 as a new town on the riverside marshes of south-east London between Plumstead and Erith. It was scheduled for completion in 1974 but was never fully finished and the projected population of 60,000 for the new town was downgraded to 45,000 by the end of the 1970s. From then around 400 houses were being built annually and by 1982, the population stood at 20,000. Since 2014 the managment and regeneration of the area has come under the aegis of Peabody.

Housing, Mangold Way, Thamesmead, London: the maisonette block

RIBA113805
Greater London Council. Department of Architecture & Civic Design
NOTES: Thamesmead was planned in 1965-1966 as a new town on the riverside marshes of south-east London between Plumstead and Erith. It was scheduled for completion in 1974 but was never fully finished and the projected population of 60,000 for the new town was downgraded to 45,000 by the end of the 1970s. From then around 400 houses were being built annually and by 1982, the population stood at 20,000. Since 2014 the managment and regeneration of the area has come under the aegis of Peabody.

Housing, Thamesmead, London: one of the elevated walkways

RIBA113813
Greater London Council. Department of Architecture & Civic Design
NOTES: Thamesmead was planned in 1965-1966 as a new town on the riverside marshes of south-east London between Plumstead and Erith. It was scheduled for completion in 1974 but was never fully finished and the projected population of 60,000 for the new town was downgraded to 45,000 by the end of the 1970s. From then around 400 houses were being built annually and by 1982, the population stood at 20,000. Since 2014 the managment and regeneration of the area has come under the aegis of Peabody.

Housing, Thamesmead, London: the tower blocks viewed from podium level

RIBA113816
Greater London Council. Department of Architecture & Civic Design
NOTES: Thamesmead was planned in 1965-1966 as a new town on the riverside marshes of south-east London between Plumstead and Erith. It was scheduled for completion in 1974 but was never fully finished and the projected population of 60,000 for the new town was downgraded to 45,000 by the end of the 1970s. From then around 400 houses were being built annually and by 1982, the population stood at 20,000. Since 2014 the managment and regeneration of the area has come under the aegis of Peabody.

Housing, Thamesmead, London: a refurbished block

RIBA113817
Greater London Council. Department of Architecture & Civic Design
NOTES: Thamesmead was planned in 1965-1966 as a new town on the riverside marshes of south-east London between Plumstead and Erith. It was scheduled for completion in 1974 but was never fully finished and the projected population of 60,000 for the new town was downgraded to 45,000 by the end of the 1970s. From then around 400 houses were being built annually and by 1982, the population stood at 20,000. Since 2014 the managment and regeneration of the area has come under the aegis of Peabody.

Housing, Thamesmead, London: the podium level

RIBA113818
Greater London Council. Department of Architecture & Civic Design
NOTES: Thamesmead was planned in 1965-1966 as a new town on the riverside marshes of south-east London between Plumstead and Erith. It was scheduled for completion in 1974 but was never fully finished and the projected population of 60,000 for the new town was downgraded to 45,000 by the end of the 1970s. From then around 400 houses were being built annually and by 1982, the population stood at 20,000. Since 2014 the managment and regeneration of the area has come under the aegis of Peabody.

Southmere Towers, Southmere Lake, Southmere, Thamesmead, London: the tower blocks seen from across the lake

RIBA113819
Greater London Council. Department of Architecture & Civic Design
NOTES: Thamesmead was planned in 1965-1966 as a new town on the riverside marshes of south-east London between Plumstead and Erith. It was scheduled for completion in 1974 but was never fully finished and the projected population of 60,000 for the new town was downgraded to 45,000 by the end of the 1970s. From then around 400 houses were being built annually and by 1982, the population stood at 20,000. Since 2014 the managment and regeneration of the area has come under the aegis of Peabody.